OTTO Q&A from the Director of Planning & Technology at Champion Industries

1.  How difficult is it to initially install OTTO?

Dead easy is the straight answer. We relied on you to install, and you installed in the predicted 1 hour.  

2.  Would you install it on a test system or on the production system?

Production system is another easy answer. I use OTTO as the ideal prototype when talking to business contacts about “add-on” products. It is non-invasive; it only reads data from our ERP files. I know the implementation is 100% safe because no ERP files are ever updated (read corrupted) by OTTO.

3.  How difficult was it to implement OTTO? Was there a negative impact on daily operations?

There is a learning curve involved in using any new tool that has value to add. OTTO implementation is very low on the impact scale, but I would strongly recommend that a prospective client plan on investing in education and practice. OTTO implementation is low impact. No valuable tool is “no impact”.

Click here to learn more about OTTO

Previous Article Is the Crossroads Analytics Dashboard Product Better than Spreadsheets?
Next Article What do you get with IDF?
Print
23534 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Fiscal, Reporting and Tax Periods can have status Open, Closed or Final Closed. If a period is Closed or Final Closed, you cannot post entries to those periods. If a period is Closed, you can re-set it to Open and post entries. If a period is Final Closed, you cannot post and you cannot set it back to Closed or Open.

A Provisional Close is run at year-end to bring the balances forward for the new year without having to close the previous year. A Provisional Close can be run as many times as you like. After a Final Close, a Provisional Close cannot be run.

The Provisional Close allows you to continue into the new year with all financial reporting and not have to rush with the Final Close until all adjusting entries are made and any final signoffs have been completed.

In Baan IVC, plan items on the lowest plan level were automatically actual items (not product families). All plan items on higher plan levels were product families.

The relationship between a product family and items on lower plan levels was defined in a planning bill of material.

In Infor LN, every family item must be defined in the Item Base Data module. A family item can exist on any plan level. The relationship between a family item and items on lower plan levels is defined in aggregation relationships.

Aggregation relationships in Infor LN are much more flexible than the planning bills of material in Baan IV. For example, users can define aggregation relationships between items on the same plan level.

First157158159160162164165166

Theme picker

Categories