Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
15484 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

In LN, the People package is used to register the employee’s hours and expenses. To support the People package, the Employees - General (tccom0101m000) session only contains the general employee data.

The title of the Employees - General (tccom0101m000) session was changed to Employees – General (tccom0101m000).

From the Employees - General (tccom0101m000) session, users can start the following sessions to define the more specific employee data:

  • Employees - People (bpmdm0101m000).
  • Employees - Project (tppdm8101m000).
  • Employees - Service (tsmdm1140m000).
  • Skills by Employee (tcppl0120m000).
  • Employees by Team (tcppl0150m000).
  • Roles by Employee (tcppl0170m000).

After users define the employees, users can also start the listed sessions from the Employees Dashboard (bpmdm0101m100) session in People.