Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.
This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.