Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
Previous Article Partner News: How does Infor LN fit the industries that it serves?
Next Article Why should you look at OTTO? Let’s see what an OTTO customer has to say:
Print
30912 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

How do I assign an unallocated payment to a purchase invoice when the document dates are not the same?

When trying to assign an unallocated payment, it is possible that the purchase invoice is not displayed in session Assign Unallocated / Advance Payments to Invoices (tfcmg2106s000), even though it is showing in the open entries. This can happen when the document date of the unallocated payment lies before the document date of the purchase invoice you want to assign it to. There are 2 ways to handle this...

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

First1415161719212223Last

Theme picker

Categories