Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Frank Petrasio

Infor M3 & Movex Tip of the Week: What inbound and outbound BODs are available for M3?

Outbound BODs from M3 to integrated applications
This table shows the BODs that are available with Infor M3. Where the product column is blank, the BOD is not currently used by interfacing products, but the BOD is generated by M3 and is available to be processed through ION and any application that is set up to receive it.

Read the full list of outbound and inbound BODs from M3 to integrated applications>

Previous Article Infor LN & Baan Tip of the Week: What is Included with Infor Operating Service (Infor OS)?
Next Article Infor M3 Webinar: Consumer Use Tax 101: What's all the fuss about for manufacturers and distributors?
Print
26740 Rate this article:
5.0
Frank Petrasio

Frank PetrasioFrank Petrasio

Other posts by Frank Petrasio

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

Watch this short video created by Infor which discusses the single/multi-logistic and finance concepts from Baan IV and Baan V and how that has changed in Infor LN with the introduction of Sites. With the Site concept and especially with the Job Shop by Site concept much more flexibility is provided.

Click to play Company versus Site Infor Video (16:19)

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is...