Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate the cumulative lead time (also called “the Critical Path”) for you.


Infor LN does not differentiate between the two. It is simply Enterprise Planning EP with one set of planned orders. It's possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists in the purchase and manufactured planned items. It has non-critical and critical lead time based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V

Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN

Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Contact us today to learn more:  800.762.2077 | solutions@crossroadsrmc.com

Previous Article LX User Group Event: Infor Partner Spotlight | Crossroads RMC
Next Article Infor LX & BPCS Tip: MPS Planned vs. MRP Planned
Print
19439 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

Manual     Physical     Inventory

While it may be accurate (and I say MAY), is a Manual Physical Inventory the right way? Best practices would say absolutely not!

The better way is implementing Cycle Counting. Why Cycle Counting instead of a full physical inventory? With a cycle count, the count focuses on a selected range of stock that can be carried out in parallel with a company’s normal operations. Cycle Counts represent a streamlined method of inventory management to ensure less disruption on the business processes associated with receiving, consuming, or dispatching of stock. 

The “freeze” is no longer required, your staff doesn't need to work long hours over the holidays, and you get accurate inventory counts all year long! Crossroads RMC can help you implement Cycle Counting efficiently and painlessly, contact us today to get started. 800.762.2077

Year-end is always a busy time and it is easy to forget things that must be done in your ERP system to close out the year properly and also set you up for a good start to the following year. Here are some things that you should make sure to add to your to-do checklist:

The year-end close process provides an opportunity to:

_____ Remove discontinued items.

_____ Remove sold purchase receipts.

_____ Remove lot attributes for sold lots.

_____ Update standard cost based on current cost field (for environments without Manufacturing only).

Prepare for Year-End Close

_____ Conduct full physical...

First2324252628303132Last

Theme picker

Categories