BPCS/LX Tip of the Week: Top Down Shop Order Schedule

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Previous Article Baan/LN Tip of the Week: Back Dating Cycling Counting Orders
Next Article Infor LX Roadmap – PowerPoint Presentation
Print
46618 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

To use the ‘Use-Up’ or ‘Alternative’ functionality the correct ATP settings of the use-up item must be defined. Order Planning makes use of ATP to determine if there is still supply available. The component needs to have a CTP horizon greater than 0. Then a top down item selection should be chosen when generating order planning in order for the ATP checks to be done and for the system to plan for the correct components.

Selecting the 'top down item' box when generating order planning is essential because when order planning is generated for only the top level item the components aren't "really" planned for. But when a top down selection is run, the system goes through the BOM and plans for each component accordingly.

Transactions to be mapped - In the mapping scheme, you must define the ledger mapping and the dimension mapping for these types of transactions:

  1. Financial integration transactions resulting from logistic events in Operations Management.
  2. General Ledger transactions.
  3. Procurement card transactions in Accounts Payable.


In addition, to support dimension accounting...

First2425262729313233Last

Theme picker

Categories