Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
7700 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

As crazy as it sounds, we’re about to enter the 4th Quarter of 2021. How are you doing on your 2021 goals? Planning for 2022 projects? Maybe it's time to get more out of your Infor ERP system.

TIME TO UPGRADE or NOT?

Is an upgrade to the latest version of Infor LN the goal for 2022? If so, Crossroads RMC brings 35+ years of industry experience to the table to ensure that your upgrade achieves the results you’re looking for and does so on time and on budget. Our goal is to delight your users and maximize the efficiencies that your business can gain from implementing best-of-breed business practices.

Crossroads RMC's team of expert consultants will...

You may want to restructure your warehouse with new bin codes and new bin characteristics. You will not undertake this kind of activity very often, but situations can occur where a reclassification is necessary to achieve or maintain a more efficient operation. In this case, you may want to remove a given warehouse location. It can be done, but you must be aware of the following:

A location cannot be removed if any of these conditions exist:

  1. Any outstanding inbound advice for the item.
  2. Any outstanding outbound advice for the item.
  3. Any unprocessed cycle counting order/adjustment order lines.
  4. Any cycle counting data.