Crossroads RMC is proud to enter their 21st year in partnership with Paccar for Baan data collection

In 1998, Paccar, Inc. chose Crossroads RMC to be their data collection partner for Baan IV. That partnership has grown over the years and now incorporates almost 200 data collection licenses and 15 different Crossroads applications that run on mobile devices throughout Paccar’s facility. This year, Paccar has elected to extend the Crossroads Data Collection - Web Collect to some of their 3rd party contractors in order to support an increase in production. With the installation of the Crossroads Data Collection - Web Collect, the subcontractors will be able to complete sub-assembly activities and inventory transfers all within Paccar’s Baan system which the subcontractors will be accessing via a point to point solution built for them.

Previous Article Baan / LN Tip of the Week: Analyzing Inventory Adjustments – 10.6
Next Article BPCS / LX Tip of the Week: Inventory Period Balance Freeze
Print
38078 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

124678910Last

Theme picker

Tips: LN | Baan

When attempting to post to a ledger account, users may occasionally encounter an error indicating that the ledger account is blocked. To resolve this issue, navigate to the Chart of Accounts session (tfgld0508m000) and select the Miscellaneous tab. Once there, review the Blocking field. The available settings are:

  1. Free
  2. Blocked for manual input (integration transactions and other automatic transactions can be posted with this setting)
  3. Blocked for all purposes.