Baan/LN Tip of the Week: Purchase Inquiry

In Baan IV Purchase Control, the purchase inquiry procedure enables user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.

In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
    1. Price
    2. Quantity
    3. Vendor rating
    4. Delivery dates
    5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: Using Pre-Assigned Lot Numbers
Next Article Four Digital Trends Manufacturers Should Watch for in 2018
Print
38811 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

The planning data for the method of manufacturing is defined in Routing. A routing consists of operations, with each operation identifying the last to be carried out in a work center and/or on a certain machine defined for a specific site.

Routings can be as follows:

  • Standard Routing - A generic routing that can be attached to multiple items
  • Item specific - A routing that is applied to one item
  • Network routing - A routing containing sequentially ordered operations and parallel operations
  • Order quantity dependent routing - A routing that is defined for a specific quantity of items

You use the Routing module to record routings for manufactured items. You can define the following:

To improve performance and reduce database growth, deleting records is highly effective. The disadvantage of deleting records is that data is no longer available. Usually, however, not all records need to be saved. For example, line activities are stored by warehouse. Normally, you do not need to keep these records. Therefore, after closing a warehouse order, line activities can be removed. The User's Guide for ERP LN Archiving and the corresponding Baan IV/V Guides describe several sessions you can use to delete old data. Other data such as items and business partners can be reviewed once in a while, after which you can delete the data you no longer need. For every order and contract table, a session is available to archive and delete old orders. In these sessions, you can specify several characteristics to select the orders to be removed, such as date or status. Run these sessions on a regular basis.