Infor LN & Baan Manufacturing Tip: All About Routings

The planning data for the method of manufacturing is defined in Routing. A routing consists of operations, with each operation identifying the last to be carried out in a work center and/or on a certain machine defined for a specific site.

Routings can be as follows:

  • Standard Routing - A generic routing that can be attached to multiple items
  • Item specific - A routing that is applied to one item
  • Network routing - A routing containing sequentially ordered operations and parallel operations
  • Order quantity dependent routing - A routing that is defined for a specific quantity of items

You use the Routing module to record routings for manufactured items. You can define the following:

â–ª Work centers - A work center is where production activities are performed. Resources, such as people and machines, are linked to a work center. A work center is a group of resource units used as a functional planning unit. The operation rate code, which is linked to the work center, is used to calculate the standard cost of an item or the estimated and actual costs. The capacity load on a work center is used in the planning of production. Work centers can be part of enterprise units used for multi-company modeling purposes.

â–ª Machines - Machines are linked to work centers and are used to plan operations. The rate defined for a machine is used to calculate the actual machine costs. The capacity load on a machine is used for production planning.

â–ª Reference operations - Classified according to the nature of the work performed, reference operations are used to describe activities that take place in the job shop. Reference operations are linked to operation rate codes, which are used to calculate the standard cost of an item or the estimated and actual costs. Reference operations are used in production planning.

â–ª Operations - The operation data for standard and customized manufactured items is maintained with operations. Operation data is stored and maintained for standard items and customized items. A series of operations are performed to manufacture an item. The sequence of operations is defined as a routing in operations. Yield and scrap are defined per operation.

â–ª Norm times - The run time and production rate of an operation are determined using norm tables. After a matrix is defined for two physical characteristics, such as length and width you can maintain a set of standard operation times for the X-Y coordinates. When tasks and routings are defined, the run time and production rate can be calculated by using a norm table.

â–ª Skills - Certain skills may be mandatory to perform a specific operation. To ensure employees assigned to an operation possess the necessary knowledge, skills are linked to both employees and operations.

Previous Article Infor LX & BPCS Manufacturing Tip: Backward Scheduling
Next Article Infor LN & Baan Finance Tip: What Can You Do in the Financial Statements Module?
Print
24843 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Customer Defined Fields (CDFs) can be added to tables, screens, reports and BODs and validation and calculation logic can be defined around those fields.

Use the CDF concept to store additional data in the standard Infor LN tables. The CDF definitions are stored separately from the table definitions in the Data Dictionary. For the end user, the CDFs behave in the same way as the standard fields, if defaulting, validations, etc. are built using the CDF logic of the table extension point. The session extension point also has features for the CDFs.

CDFs are configured per package combination. This implies that when moving your companies from one package combination to another, the CDF definitions must be present in the target package combination. Otherwise you lose the data in the CDFs.

The package includes numerous reports and sessions to view the variances in a way that Finance can identify problems based on the Finance Integration Transactions in the General Ledger.

There are a few main sessions with many detailed sessions linked to them. The reports can be run from the main Print Production Order Variance Reports or in the individual detailed session.

Sessions included in the report package:

1. Print Finalized Trans – Variance Reports.

a. Financial Trans. by L/Acct – Prod. Order Variances - Recap

b. Financial Trans. by L/Acct – Prod. Order Variances – Details

2. Update Production Order Variances (updates special variance table).

3. Production Order Variance Overview – Main view

a. Production Order Variance Details

b. Price Variance Details – Material Variances

c. Price Variance Details – Operation Variances

d. Efficiency Variance Details – Material Variances

e. Efficiency Variance Details – Operation Variances

f. Efficiency Variance Details – Reject Variances

g. ACO Variance Details – Reject Variances

h. Accept Production Order Variances

i. Un-accept Production Order Variances

j. Finally Accept Production Order Variances

4. Print Production Order Variance Reports:

a. Production Order Variance – Overview

b. Production Order Price Variance – Material Revaluation

c. Production Order Price Variance – Operation Revaluation

d. Production Order Efficiency Variance – Material

e. Production Order Efficiency Variance – Operation

f. Production Order Efficiency Variance – Rejects

g. Production Order ACO Variance – Rejects-Additional Costs

5. Delete Production Order Variances (used to redo a month)

Contact Kathy Barthelt to learn more.