Infor LN & Baan Tip: Project Status Options

Ever wonder what the implications are of choosing one project status versus another?

Here is the explanation of project status possible values:

Free
You can carry out project engineering. This means that you can:

  • Define the project master schedule (PMS) by using the Project Control module.
  • Maintain the project structure.
  • Maintain the customized product structure by using customized bills of material and routing sheets.
  • Carry out project estimating.

Simulated
You simulate the rough capacity requirements planning and the detailed material and resource requirements planning (RRP) based on the network planning. The capacity requirements for a simulated project are visualized separately. Infor LN (ERP LN) generates planned RRP purchase orders, planned production orders, and PRP warehouse orders for customized items. However, those orders cannot be released. Moreover, the RRP does not allocate standard items to the project.

Active
This status indicates the project's execution stage. You can release planned orders so that the required purchase and production activities can be actually started and completed.

Canceled
The project has been canceled. You cannot release new orders for the project, but you can, however, finish pending logistical activities. You can close a canceled project, but a project can also remain canceled. If the project remains canceled, be aware that the final costs are not posted to Financials, and that WIP can still exist for completed orders. Costs are only posted if you close the project.

Finished
As far as manufacturing is concerned, the project is finished. Also, all purchase and production activities have been completed or closed, and all sales orders have been delivered for the project.

Closed
Financially, the project has been closed. This means that the financial project results have been computed. Financial project transactions can no longer be posted to the project.

To be Closed
If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted on the financial companies of the sales office, service department, and/or warehouse instead of on the financial company of the PCS project. If internal invoices are sent from the PCS project to those departments, and the internal invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.

Archived
The project has been archived. This means that all project data has been stored in archive files and is removed from the original files.

Previous Article Infor LX & BPCS Tip: How Items Are Selected for a Cycle Count
Next Article Collaborate IN-PERSON With Infor LN Users
Print
20212 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Customer Defined Fields (CDFs) can be added to tables, screens, reports and BODs and validation and calculation logic can be defined around those fields.

Use the CDF concept to store additional data in the standard Infor LN tables. The CDF definitions are stored separately from the table definitions in the Data Dictionary. For the end user, the CDFs behave in the same way as the standard fields, if defaulting, validations, etc. are built using the CDF logic of the table extension point. The session extension point also has features for the CDFs.

CDFs are configured per package combination. This implies that when moving your companies from one package combination to another, the CDF definitions must be present in the target package combination. Otherwise you lose the data in the CDFs.

The package includes numerous reports and sessions to view the variances in a way that Finance can identify problems based on the Finance Integration Transactions in the General Ledger.

There are a few main sessions with many detailed sessions linked to them. The reports can be run from the main Print Production Order Variance Reports or in the individual detailed session.

Sessions included in the report package:

1. Print Finalized Trans – Variance Reports.

a. Financial Trans. by L/Acct – Prod. Order Variances - Recap

b. Financial Trans. by L/Acct – Prod. Order Variances – Details

2. Update Production Order Variances (updates special variance table).

3. Production Order Variance Overview – Main view

a. Production Order Variance Details

b. Price Variance Details – Material Variances

c. Price Variance Details – Operation Variances

d. Efficiency Variance Details – Material Variances

e. Efficiency Variance Details – Operation Variances

f. Efficiency Variance Details – Reject Variances

g. ACO Variance Details – Reject Variances

h. Accept Production Order Variances

i. Un-accept Production Order Variances

j. Finally Accept Production Order Variances

4. Print Production Order Variance Reports:

a. Production Order Variance – Overview

b. Production Order Price Variance – Material Revaluation

c. Production Order Price Variance – Operation Revaluation

d. Production Order Efficiency Variance – Material

e. Production Order Efficiency Variance – Operation

f. Production Order Efficiency Variance – Rejects

g. Production Order ACO Variance – Rejects-Additional Costs

5. Delete Production Order Variances (used to redo a month)

Contact Kathy Barthelt to learn more.