Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
7803 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

The package includes numerous reports and sessions to view the variances in a way that Finance can identify problems based on the Finance Integration Transactions in the General Ledger.

There are a few main sessions with many detailed sessions linked to them. The reports can be run from the main Print Production Order Variance Reports or in the individual detailed session.

Sessions included in the report package:

1. Print Finalized Trans – Variance Reports.

a. Financial Trans. by L/Acct – Prod. Order Variances - Recap

b. Financial Trans. by L/Acct – Prod. Order Variances – Details

2. Update Production Order Variances (updates special variance table).

3. Production Order Variance Overview – Main view

a. Production Order Variance Details

b. Price Variance Details – Material Variances

c. Price Variance Details – Operation Variances

d. Efficiency Variance Details – Material Variances

e. Efficiency Variance Details – Operation Variances

f. Efficiency Variance Details – Reject Variances

g. ACO Variance Details – Reject Variances

h. Accept Production Order Variances

i. Un-accept Production Order Variances

j. Finally Accept Production Order Variances

4. Print Production Order Variance Reports:

a. Production Order Variance – Overview

b. Production Order Price Variance – Material Revaluation

c. Production Order Price Variance – Operation Revaluation

d. Production Order Efficiency Variance – Material

e. Production Order Efficiency Variance – Operation

f. Production Order Efficiency Variance – Rejects

g. Production Order ACO Variance – Rejects-Additional Costs

5. Delete Production Order Variances (used to redo a month)

Contact Kathy Barthelt to learn more.

Graphical representation makes complex concepts—like the intricacies of an ERP system—more universal, relatable and easy to understand.

ERP dashboards gather and visualize critical metrics from across the organization, offering insight into the performance, outlook and interconnectivity of business processes.

By setting up ERP dashboards that illustrate key metrics and compellingly communicate operational performance, key stakeholders will have a clear picture of the health of the business—and make better, more informed business decisions as a result.

The Crossroads Analytics Dashboard has preconfigured views for all of the following:

 Infor LN & Baan
  • Accounts Payable
  • Accounts Receivable
  • Journal
  • Booked Sales
  • Invoiced Sales
  • Production
  • Receipts
  • Purchase Orders
  • Inventory

To learn more visit our Analytic Dashboard webpage.