Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: How is Your Productivity?
Next Article Demand-Driven Manufacturing Metrics that Drive Action - White Paper
Print
27490 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

123457910Last

Theme picker

Tips: LN | Baan

Frequently Asked Questions (KB2316174)

For Infor LN a framework has been developed to support REST API-based services for lean integrations. This framework is now made available for the LN application. This KB answers some common questions you may have and procedures that are needed for using the LN Rest APIs.

More details on these topics can be found in the Infor LN REST API Administration Guide.

FINANCE: Can accounts receivable invoices be uploaded into LN using Excel?
Yes, this is possible, by following the steps below:

1. Maintain a batch

2. ....

OPERATIONS: MPS Planned vs. MRP Planned
When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

Master Scheduled Items:

TECHNOLOGY: Are you running the latest Infor components?
Always good to stay on top of new releases for your various Infor components. Here is a list of knowledge base articles that you can check for the components listed below: