Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
15389 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

From John O'Kelly's article on Manufacturing.net:

"Regardless of industry, efficiency gains and increased speed provide a competitive edge. The ever-increasing competition in the manufacturing world makes it necessary to find new, efficient ways to speed up the process while remaining accurate and productive. While flying robots and miracle technologies may promise to reshape the industry, we still have a way to go until full automation, and thus the most important asset on the manufacturing floor in 2019 will remain its people.

In 2019, the focus will undoubtably be increasing efficiencies, and this can be achieved through investing in employees, equipping them with the proper techniques and tools. An invested labor force will limit mistakes on the manufacturing floor and improve throughput at every level of the process."

Here are a few best practices to increase efficiency on the manufacturing floor in 2019:

  1. Invest in your labor force
  2. Prioritize quality assurance
  3. Improve labeling errors

You can read the full article with detailed descriptions at: https://blog.safe.com/

Optimize Your Manufacturing Today!

Baan & LN Tip of the Week: Get Real!

You’ve got an ERP system, so everything should be real-time and everyone should have access to information in real-time, right? RIGHT?!

Why not? Why are there spreadsheets, and separate Access databases off to the side?

Data loses value over time, so why not give everyone up to date, accurate information all the time? Take a look at those silos of information and see how you can eliminate them. Your business will benefit greatly as a result.