Infor LN & Baan Tip: What conditions must exist before changing an item's inventory unit?

Is there a procedure for changing an item’s inventory unit? What conditions must exist before it can be done?

Once inventory transactions (receipts or issues) have occurred for an item, the inventory unit cannot be changed. If only orders have been placed against the item (sales or purchase), the inventory unit can be changed if these orders are removed and the economic stock of the item is zero.

The reason that the inventory unit cannot be changed once transactions have been made is due to how transactions are recorded. The inventory transactions are recorded in units. These units are the inventory unit of the item. The inventory unit is not held in this table, however. The inventory unit is held on the item data. For example, if 5 pieces (pcs) of an item are issued and the inventory unit is later changed to pounds (lbs), there will be a mismatch in the inventory history of the item. In the past, the item was issued as pcs, and now the item master inventory unit is lbs. As the inventory unit is not date effective, the inventory has then been issued in two different units (pcs and lbs), but there is no method to recognize this difference.

Previous Article Infor LX & BPCS Tip: 4 Approaches to Customizing LX / BPCS - Preparing for a Future Upgrade
Next Article Reskilling and Upskilling Your Staff – Why You Shouldn’t Ignore This
Print
15792 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

I'm reposting this checklist for things to consider in order to finish out the year, and plan for next year…

  • Are your accounting records up to date so that you can make a projection of how the current year will turn out?
  • Are all account reconciliations currently up to date to facilitate the closing of the books after year end?
  • Are there accounts receivable that should be reserved for or written off prior to the end of the year?
  • If your business carries inventory, do you need to plan a physical count as of the end of the year?
  • Has depreciation on your fixed assets been recorded during the year? Have you considered depreciation on current year additions?
  • Have all new asset purchases and bank loans been recorded on your books?
  • Are there any liabilities, for example, pending legal actions or warranty issues, which will need to be recorded prior to year end? 
  • Do you have a plan in place to properly “cut-off” revenue at year end to properly match revenue and expense?
  • Will there be bonuses, profit sharing contributions or discretionary retirement plan contributions paid prior to the end of the year? How will these payments affect cash flow?
  • Will you be in compliance with your bank covenants at year end?
  • Do you need to make arrangements to receive statements as of the end of the year for cash value of life insurance, loan balances, etc.?

Optimize Your Manufacturing Today!

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if database is also running on same server as application)

Need help getting on a newer porting set? We'd be happy to help.

Optimize Your Manufacturing Today!

First8586878890929394Last

Theme picker

Categories