Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

BPCS/LX Tip of the Week: Email Distribution Lists

Anthony Etzel 0 24088 Article rating: No rating

Email Distribution Lists are new in Infor LX Version 8.

With this feature, users can create groups to which they may add internal or external email addresses, and in turn, use the name of the group when sending out the email.

The email distribution list eliminates the need for a program change if recipients need to be added to or deleted from the group. 

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Clusters in LN

Kathy Barthelt 0 32472 Article rating: No rating

A cluster is a group of one or more warehouses in a particular geographical area. You can plan an item by cluster (geographical area).

To enable this, you can set up multiple plan items for one item. You always define one plan item without a cluster indication and multiple plan items with a cluster indication. A plan item with a cluster is called a clustered plan item, and a plan item without cluster is called the non-clustered plan item.

The plan items in the clusters can be supplied not only by distribution, but also through purchase and production. In this way, you can, for example, plan local purchasing in a cluster (geographical area). You can also plan supply from multiple sources.

 

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: When More = Less

Anthony Etzel 0 22681 Article rating: No rating

Do you have bottlenecks in your process due to product changeovers or breakdowns?
Maybe the answer is adding redundancy in the department where you are experiencing the problem. A duplicate machine setup can allow for double the capacity during high production periods. It can also eliminate the need to swap out tools or other materials due to different production runs. When breakdowns occur, equipment can be swapped out to keep production moving while repairs are being made.

Planning for this keeps production levels high.

 

 

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: When More = Less

Kathy Barthelt 0 31661 Article rating: No rating

Do you have bottlenecks in your process due to product changeovers or breakdowns?

Maybe the answer is adding redundancy in the department where you are experiencing the problem. A duplicate machine setup can allow for double the capacity during high production periods. It can also eliminate the need to swap out tools or other materials due to different production runs. When breakdowns occur, equipment can be swapped out to keep production moving while repairs are being made.

Planning for this keeps production levels high.

 

 

 

Optimize Your Manufacturing Today!

RSS
First979899100102104105106Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Absorbing Cost Items into Projects

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items:

    • If needed, create the cost items.
    • Create a purchase order for the cost items without referencing a project number.
  4. Matching PO to Costs:

    • When matching the purchase orders in session tfacp2107m000, select "Add Costs" from the specific menu on the toolbar (you'll need to be in the matching details to access this).
    • This will open session tfacp1133s000, where you will enter the previously specified ledger account number.
    • Once done, the "PCS Transactions" option on the toolbar becomes available. Selecting this brings up session tipcs3140m000 (General Actual Project Costs).
       
  5. Disbursing Costs to Projects: In session tipcs3140m000, the PO costs for the cost items can be disbursed to any open and active project.

Since these are cost items, they won't go into stock. The key is ensuring that the cost disbursement ("Add Costs") is correctly linked to the appropriate project, giving users visibility of the cost items as general project costs.
 

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Adding a Timestamp to LN Standard Tables
Print
5049 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories