Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 34276 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 26382 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 45787 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i

Kathy Barthelt 0 27468 Article rating: No rating

Crossroads RMC is proud to announce the official release of NextTrack Sales – a sales analysis tool for Baan, LN, and IBM i. NextTrack Sales allows you to get the “big picture”, or get down into the finer details. The tool provides a sophisticated pivot grid and charting functionality, export to Excel, PDF printing, and emailing capabilities to bring your sales data to life. Analyze your Baan Sales data to examine trends, identify market opportunities, and much more. Click here for more details.

RSS
First124125126127129131132133Last

Theme picker

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: Support for IBM i 7.3 and Infor LX Products

On September 30, 2022, IBM® announced the end of support of IBM i operating system 7.3 effective September 30, 2023. In line with IBM’s support policy, Infor will no longer support LX and related products on IBM i 7.3 after May 31, 2024. All Infor LX releases, patches, and related solutions are planned to be delivered and compiled at IBM i 7.4, effective June 1, 2024. These deliverables will install and function on version 7 release 4 (IBM i 7.4) and above. This will require that your operating system is at a minimum release level of IBM i 7.4.

This policy extends to other Infor LX-related technologies including WebTop, System i Workspace (SiW), and Infor Development Framework (IDF).

Action Steps If you have not done so already, we recommend that you start planning and completing your upgrade to IBM i 7.4 or above prior to June 1, 2024. After this date, if you register a support call with Infor Support, and your application still runs on IBM i 7.3 or older, you may be requested to upgrade to a supported version of the IBM i operating system.

In addition, we invite you to log on to Infor Support to view and download important information regarding Infor LX. Knowledge Base (KB) articles have been created to proactively provide you with information regarding this Announcement. ​Please consider clicking on the “Subscribe” feature within each KB article to receive notifications. Once you have subscribed, you will receive notifications when they are updated.

  • View KB article 1397381 | Infor LX Product Bulletins and Announcements
  • View KB article 1947086 | Infor BPCS/LX Product Lifecycle Policy


If you need assistance in planning this project, Crossroads RMC is happy to help you strategize, and create project plans, test plans, 3rd party product due diligence, and cutover assistance. Contact us today to learn more. 800.762.2077  | solutions@crossroadsrmc.com

Print
12940 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

x

Categories