BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3

Anthony Etzel 0 34496 Article rating: No rating

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 47356 Article rating: 5.0

Pros/Cons of Multi Finance / Single Logistic Company Set-Up


Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different enterprise units included in the logistics company.
Centralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
Logistics data visible to all logistics users – a pro if this is what is desired.
One BOM, Routing, and Cost for each item.

 

RSS
First127128129130132134135136Last

Theme picker

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: Support for IBM i 7.3 and Infor LX Products

On September 30, 2022, IBM® announced the end of support of IBM i operating system 7.3 effective September 30, 2023. In line with IBM’s support policy, Infor will no longer support LX and related products on IBM i 7.3 after May 31, 2024. All Infor LX releases, patches, and related solutions are planned to be delivered and compiled at IBM i 7.4, effective June 1, 2024. These deliverables will install and function on version 7 release 4 (IBM i 7.4) and above. This will require that your operating system is at a minimum release level of IBM i 7.4.

This policy extends to other Infor LX-related technologies including WebTop, System i Workspace (SiW), and Infor Development Framework (IDF).

Action Steps If you have not done so already, we recommend that you start planning and completing your upgrade to IBM i 7.4 or above prior to June 1, 2024. After this date, if you register a support call with Infor Support, and your application still runs on IBM i 7.3 or older, you may be requested to upgrade to a supported version of the IBM i operating system.

In addition, we invite you to log on to Infor Support to view and download important information regarding Infor LX. Knowledge Base (KB) articles have been created to proactively provide you with information regarding this Announcement. ​Please consider clicking on the “Subscribe” feature within each KB article to receive notifications. Once you have subscribed, you will receive notifications when they are updated.

  • View KB article 1397381 | Infor LX Product Bulletins and Announcements
  • View KB article 1947086 | Infor BPCS/LX Product Lifecycle Policy


If you need assistance in planning this project, Crossroads RMC is happy to help you strategize, and create project plans, test plans, 3rd party product due diligence, and cutover assistance. Contact us today to learn more. 800.762.2077  | solutions@crossroadsrmc.com