Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3

Anthony Etzel 0 34807 Article rating: No rating

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 47823 Article rating: 5.0

Pros/Cons of Multi Finance / Single Logistic Company Set-Up


Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different enterprise units included in the logistics company.
Centralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
Logistics data visible to all logistics users – a pro if this is what is desired.
One BOM, Routing, and Cost for each item.

 

RSS
First128129130131133135136137Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Order Quantity Dependent Routings vs Default Routings

Order quantity-dependent routings

An automatically selected routing tailored to a specific production order quantity is useful. An example would be if the production order quantity is large, a routing with high production rates is used; If the order quantity is small, another routing is selected.

You can set up these quantity-dependent routings:

  • Select the Quantity-dependent Routing check box in the Item - Production (tiipd0101m000) session.
  • Enter the routing codes in the Item - Routings (tirou1101m000) session. Enter the maximum quantity for which a routing is valid in the Up to Quantity field.

Note: If multisite functionality is activated, the routings available may vary per site on the job shop bill of material selected. Differences in routings have an impact on the standard cost calculation.

Default routing

If the Quantity-dependent Routing check box is not selected, the default routing applies to an item. However, this default routing must also be linked to the item. To find out, LN checks the default routing code in the Default Routing field of the Job Shop Master Data Parameters (tirou0100m000) session. Next, LN checks whether the default routing code is linked to the item in the Item - Routings (tirou1101m000) session. If so, the default routing applies to the item. If the default routing is not linked to the item, no routing is used.

Previous Article Infor LN & Baan Tip & Tricks for TECHNOLOGY: Infor LN Rest API
Next Article Infor LN & Baan Tips & Tricks for FINANCE: Integration Transactions - Compression
Print
7003 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories