Anthony Etzel 0 34820 Article rating: No rating

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 47861 Article rating: 5.0

Pros/Cons of Multi Finance / Single Logistic Company Set-Up


Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different enterprise units included in the logistics company.
Centralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
Logistics data visible to all logistics users – a pro if this is what is desired.
One BOM, Routing, and Cost for each item.

 

RSS
First128129130131133135136137Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Accurate Job Costing

Standard costing is really a ‘best guess’ at labor costing -- these numbers are often inaccurate, incomplete or out of date.

Accurate job costing requires the capture of all tasks associated with a specific product or job, including direct and indirect labor in setup, production and customer service.

Inaccuracies in the collection of time allocated to machinery and the use of materials can result in the inability to properly pass those charges through to the customer, reducing company profitability.

Basically, you can’t manage what you can’t measure -- and you can’t measure what you can’t track. So the inability to track time-to task ultimately inhibits maximum utilization of the workforce. Unproductive activities remain hidden from sight -- managers don’t have the information needed to understand where wasted time exists, and therefore cannot create an action plan to remove it.

Optimize Your Manufacturing Today!

Previous Article Tip of the Week: Ways to Manage the Pain of Losing a Key Employee Before it Ever Happens
Next Article Baan/LN Tip of the Week: Month End Miscellaneous To-Do’s
Print
43451 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories