Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3

Anthony Etzel 0 34807 Article rating: No rating

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Baan/LN Tip of the Week: ERP Setup - Pros & Cons

Kathy Barthelt 0 47823 Article rating: 5.0

Pros/Cons of Multi Finance / Single Logistic Company Set-Up


Pros
Each legal entity can have its own general ledger and balance sheet.
Income statements can be generated for the different enterprise units included in the logistics company.
Centralized operations – purchasing, sales, manufacturing, planning, warehousing, etc.
Logistics data visible to all logistics users – a pro if this is what is desired.
One BOM, Routing, and Cost for each item.

 

RSS
First128129130131133135136137Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Setting Up New Employees in LN

In LN, the People package is used to register the employee’s hours and expenses. To support the People package, the Employees – General (tccom0101m000) session only contains the general employee data.

The title of the Employees – General (tccom0101m000) session was changed to Employees – General (tccom0101m000).

From the Employees – General (tccom0101m000) session, users can start the following sessions to define the more specific employee data:

  • Employees – People (bpmdm0101m000).
  • Employees – Project (tppdm8101m000).
  • Employees – Service (tsmdm1140m000).
  • Skills by Employee (tcppl0120m000).
  • Employees by Team (tcppl0150m000).
  • Roles by Employee (tcppl0170m000).

After users define the employees, users can also start the listed sessions from the Employees Dashboard (bpmdm0101m100) session in People.

Previous Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Next Article Baan/LN Tip of the Week: Default Order Frequency
Print
34273 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories