BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 38588 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 36190 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 33491 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

RSS
First135136137138140142143144Last

Theme picker

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip of the Week: Job Groups in LN

In a scenario where performing job A depends on the result of job B, it is hard to decide at what time job A must be scheduled, and how long job B runs. To handle dependent jobs, you can now create a job group. Use the Job Groups (ttaad5140m000) session to create a job group. A job group has a name, with the same characteristics as a job name, and a description. The Status and User of the job group are handled automatically.

After creating the job group, the jobs are added to the group, approximately in the order the jobs must be performed. The first job in the group (with the lowest Group Number) determines the handling of the whole job group, such as execution date and whether the job group is being repeated. If the job group is not repeating, the job group and all non-repeating jobs in the job group are deleted when the job group has run.

The dependencies of the jobs in the job group are also determined. A job in the job group can only depend on a job in the same job group with a lower job number.

You can use the specific options in the Job Groups (ttaad5140m000 andttams5640m000) sessions to change the status of the job group. The job group statuses have the same meaning as the status of the jobs and the same status changes are allowed.

Note: Job groups are only handled by the BSE service Job Scheduler Service.

Previous Article Infor LN & Baan Tip of the Week: Credit Checks for Business Partners
Next Article Infor LN & Baan Tip of the Week: Customer requested delivery date
Print
37881 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories