BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 38138 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 48386 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 34747 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 45811 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

RSS
First136137138139141143144145Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Crossroads RMC

Top 10 Things (you might not know) About Crossroads RMC

  1. Crossroads RMC has been in business since 1984 & has been an  partner since 1991
     
  2. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽
     
  3. Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓
     
  4. Our consultants have expert-level functional & technical knowledge of every version of Infor LN & Baan from Baan IVc through LN 10.8, and Infor LX & BPCS from BPCS 3.0 to LX 8.4.X. 👩🏽‍💻
     
  5. Crossroads RMC is a value-added reseller of new and refurbished data collection equipment (mobile computers, printers, RFID equipment, and more).  🚚
     
  6. Our headquarters are just outside of Chicago, but for some silly reason, our East Coast staff thinks they have the best pizza. 🍕🍕
     
  7. Our integration specialists have developed over 60 different integrations to Infor LN, Baan, Infor LX & BPCS. ⚙️
     
  8. Crossroads RMC offers 24 X 7 support to all of our customers. 💪
     
  9. Our technical consultants have developed many Infor ERP software add-on solutions like MES, Data Collection, Analytics Dashboards, Barcode Label Generation FedEx and UPS integration, VJES (Visual Job Execution Software) and more that are used by thousands of Infor users every day.
     
  10. We’ve been publishing Infor LN, Infor LX, BPCS, and Baan tips & tricks since February 2010, and most are still available on our website, with new ones added every other week! 💡💡

     

Print
12233 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

x

Categories