Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN

Kathy Barthelt 0 47005 Article rating: No rating

In Baan IV, a distinction is made between the actual ERP system and a separate planning tool which contains the Constraint Planning package. This tool was intended to work with any ERP system, not just with Baan IV. The Enterprise Planning package is now considered to be a package like any other package in Infor LN.

Users of Baan IV could choose whether they wanted to plan their supply in one of the following ways:

  • By using the MPS and MRP modules in the Manufacturing package.
  • By using the RPD and RMP modules in the Constraint Planning package.

Users of Infor LN can only use the Enterprise Planning package. The distinction between the MPS items and MRP items has been abandoned. In Infor LN, all items can be planned by using a combination of master-based planning methods and order-based planning methods.

Baan/LN Tip of the Week: Setting Up New Employees in LN

Kathy Barthelt 0 45648 Article rating: No rating

In LN, the People package is used to register the employee’s hours and expenses. To support the People package, the Employees - General (tccom0101m000) session only contains the general employee data.

The title of the Employees - General (tccom0101m000) session was changed to Employees – General (tccom0101m000).

From the Employees - General (tccom0101m000) session, users can start the following sessions to define the more specific employee data:

  • Employees - People (bpmdm0101m000).
  • Employees - Project (tppdm8101m000).
  • Employees - Service (tsmdm1140m000).
  • Skills by Employee (tcppl0120m000).
  • Employees by Team (tcppl0150m000).
  • Roles by Employee (tcppl0170m000).

After users define the employees, users can also start the listed sessions from the Employees Dashboard (bpmdm0101m100) session in People.

RSS
First138139140141143145146147Last

Theme picker

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Integrations:

It's okay, you can admit it. You have spreadsheets and separate databases that you’re keeping on the side that may or may not be tied to Baan/LN.

Do you wish they were integrated so that you didn’t have to manually go into each system to report on the data or look up information? Are you running into problems because you don’t have exposure to all of the data that is critical to running your business?

Crossroads RMC has a team of integration experts who can create the integration you’ve been dreaming about… AND we have developed RMCconnector to allow for quick and easy translation data from your front end system into a format accepted by your back end ERP. 

Contact us today to discuss how we can help you eliminate those spreadsheets and tie those “one-off” systems directly to your ERP system. 800.762.2077

Print
25953 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories