BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 322 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.


To calculate the offset, the system takes the parent lead time from the Item 
Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.


Note that the offset calculation uses only calendar records that have a blank 
work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Day: Multi-Company Taxation – LN

Kathy Barthelt 0 278 Article rating: No rating
Tax reporting is part of the financial accounting and is restricted to one country. Therefore, the LN tax handling in a multi-company structure is similar to the tax handling in a single company environment.

Tax handling in LN includes the following:

· Tax registration

For tax registration, you define the various tax details for each country in the Taxation module. In the General Ledger module of Financials, you specify the ledger accounts for the tax amounts separately for each financial company. LN can post the tax amounts calculated for a tax code to different ledger accounts in the individual financial companies, for example, in a single logistic, multi-financial company structure.

BPCS/LX Tip of the Day: Accounts Payable / Purchasing

Anthony Etzel 0 981 Article rating: No rating

You can integrate Accounts Payable (ACP) with Purchasing. ACP requires more detailed information in the Vendor file than Purchasing requires. Accounts Payable automatically checks for a valid purchase order when you

match invoices to POs and receipts. Enter any outstanding active purchase orders through PO Release, PUR500, before you can match invoices in Accounts Payable.

 

Accounts Payable can also update the Actual Cost fields in the Inventory Master file directly from vendor invoices. You must provide the following information in order for Accounts Payable to complete this update:

â–ª Define a type C inventory transaction.

â–ª Enter a valid purchase order on the Invoice Entry header screen, ACP500D2-01, or in the Next Purchase Order field on the Invoice Entry: PO Costing screen, ACP500D3-01.

â–ª Enter the information for the actual cost transaction on the appropriate lines.

Baan/LN Tip of the Day: Virtualization

Kathy Barthelt 0 39282 Article rating: No rating

The advantages of virtualization include the following:
 

• You get more out of your existing resources. Pool common infrastructure resources and break the legacy “one application to one server” model with server consolidation.

• You can reduce datacenter costs by reducing your physical infrastructure and improving your server to admin ratio. Fewer servers and related IT hardware means reduced real estate and reduced power and cooling requirements. With better management tools, you can improve your server to admin ratio so personnel requirements are reduced.

• You can increase the availability of hardware and applications for improved business continuity.

• Securely back up and migrate entire virtual environments with no service interruptions. Eliminate planned downtime and recover immediately from unplanned issues.

• Gain operational flexibility. Respond to market changes with dynamic resource management, faster server provisioning, and improved application deployment.

 

The disadvantages of virtualization include the following:

 Virtualization adds overhead to the CPU, memory, IO, and network.

 Virtualization adds an additional layer to the hardware and software stack. Therefore, additional complexity is introduced in the following circumstances:

RSS
First144145146147149151152153Last

Theme picker

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES

FINANCE
Ledger Account Blocked Error
When attempting to post to a ledger account, users may occasionally encounter an error indicating that the ledger account is blocked. To resolve this issue, navigate to the Chart of Accounts session (tfgld0508m000) and select the Miscellaneous tab. Once there, review the Blocking field. The available settings are:

  1. Free
  2. Blocked for manual input (integration transactions and other automatic transactions can be posted with this setting)
  3. Blocked for all purposes.

OPERATIONS
Absorbing Cost Items into Projects
To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items:

    • If needed, create the cost items.
    • Create a purchase order for the cost items without referencing a project number.
  4. Matching PO to Costs:

    • When matching the purchase orders in session tfacp2107m000, select "Add Costs" from the specific menu on the toolbar (you'll need to be in the matching details to access this).
    • This will open session tfacp1133s000, where you will enter the previously specified ledger account number.
    • Once done, the "PCS Transactions" option on the toolbar becomes available. Selecting this brings up session tipcs3140m000 (General Actual Project Costs).
       
  5. Disbursing Costs to Projects: In session tipcs3140m000, the PO costs for the cost items can be disbursed to any open and active project.

Since these are cost items, they won't go into stock. The key is ensuring that the cost disbursement ("Add Costs") is correctly linked to the appropriate project, giving users visibility of the cost items as general project costs.


TECHNOLOGY
Adding a Timestamp to LN Standard Tables
Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps:

  1. Enter the Tables: In this session, specify the tables for which you want to define timestamps.

  2. Convert and Reconfigure: Run the Convert to Runtime Data Dictionary (ttadv5215m000) session to convert the table definitions to the runtime data dictionary and reconfigure the tables.

  3. Restart Session: Log off and log back on to apply the changes.

IMPORTANT!
To avoid issues with locked tables, ensure that all users have logged off before starting the reconfiguration.

For more information, refer to the online help of the Convert to Runtime Data Dictionary (ttadv5215m000) session.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Ledger Account Blocked Error
Next Article Infor LN & Baan Tips & Tricks for OPERATIONS: Absorbing Cost Items into Projects
Print
733 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories