BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 343 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Database Sizing – Moving to LN

Kathy Barthelt 0 219 Article rating: No rating
The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

How Do You Measure Success in Your Business?

Anthony Etzel 0 52081 Article rating: 5.0

Business owners may measure success in different ways – some tangible, some intangible.

In order to establish how you should measure success for your business, you need to first examine how you measure your personal success. If you are a business owner, or a part of the management team of the company you work for, ask yourself these questions to see how you measure up:

Assess personal success.

1.    Am I happy in my job?

2.    Do I have passion for what I’m doing?

3.    Do I get the desired results based on the effort I’m putting in?

4.    Am I putting forth my best effort?

5.    Am I patient and allow for sufficient time to see results?

6.    Do I get respect from my co-workers?

7.    Do I have the endurance to hang in there when things get a bit rough?


Reflect on successes and failures.

After answering these questions, do you need to make any changes? Do you still have the same ambition and drive to achieve the goal? Are you content with your work, or have you come to the conclusion that you have not done your best?

To be successful...

RSS
First148149150151153155156157Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip & Tricks for OPERATIONS: Best Practices for Purchase Order Archiving / Deleting

 Here are some best practices to follow if you are considering archiving or deleting purchase order data:

  • If Financials is implemented, we recommend that you do not delete order data in a fiscal year that has not yet been fully closed. This is because the GRINYA process uses information that would be deleted by this action. For best results, check whether the logistical balance for non-invoiced receipts matches the balance of the GRINYA accounts for the periods up to which you want to delete purchase order data.
  • When a purchase order is canceled, you can only delete the purchase order and the related tables. If only a purchase order line is canceled, the line can be deleted and archived.
  • Purchase contracts must be archived before purchase orders can be archived.

You cannot delete a purchase order (line) if:

  • The linked warehouse order is closed but cannot be removed.
  • The purchase order is linked to a PCS project that is not yet archived. When the PCS project is archived, the purchase data is also archived and you can delete the purchase order.
  • A consignment replenishment order is not yet consumed completely.
  • The invoice is yet to be completely matched and approved.
  • The invoice amount is not yet inserted as turnover history.
  • The sales order or service order that's linked to the purchase order line, and for which an internal invoice must be sent from the purchas office to the sales office or service office, is not yet invoiced. In this case, you cannot delete the purchase order line before the sales order or service order is invoiced.

Previous Article Infor LN & Baan Tip & Tricks for TECHNOLOGY: Using Table Boosters to Speed Up Sessions & Processes
Next Article Infor LN / Baan Tips & Tricks for EXECUTIVES
Print
9523 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories