BPCS/LX Tip of the Week: Top Down Shop Order Schedule

Anthony Etzel 0 48655 Article rating: No rating

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Baan/LN Tip of the Week: Back Dating Cycling Counting Orders

Kathy Barthelt 0 58074 Article rating: No rating

Cycle Count Orders cannot be directly “back dated” in Baan IV, Baan V or LN, however, there are some work-arounds.

In Baan IV you can do an inventory adjustment and back date. Just set all dates on the adjustment to the date you want and Baan will post the adjustment in that period.

In LN you can do a Cycle Count/ Adjustment and again back date and Baan will post to that period.

 

Unfortunately, there is no work-around for Baan V.

BPCS/LX Tip of the Day: Inventory Management

Anthony Etzel 0 45435 Article rating: No rating

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 

Baan/LN Tip of the Day: Chart of Accounts

Kathy Barthelt 0 57977 Article rating: No rating

Zero sublevel accounts are posting level accounts. All others are parent accounts. Once the balances have been updated in the child ledger accounts, the parents are automatically updated.

Inquiries and reports can be printed or displayed either by child accounts or by parent accounts. On line drill-down is possible from either child or parent.

RSS
First158159160161163165166167Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Introducing VJES (Visual Job Execution Software)

You would be hard-pressed to completely miss the stories in the news recently about quality issues in manufacturing. The crux of the issue has been a complete focus on production and a lack of focus on quality. Yes, it is a wonderful thing to get the goods out the door, but when you’re sacrificing quality, what good is it really?

There are specifications for production for a reason. Engineering exists for a reason. If products are not built according to exact design specifications, scrap is likely to go up, rework goes up, customer returns and/or service requests go up, and customer satisfaction and overall customer confidence in your product plummets.

Is all of that worth it to get the good out the door in the shortest amount of time possible?

Every manufacturer relies on a few core measurements to manage their operations. Measurements like efficiency, productivity, capacity, labor and equipment utilization are used by manufacturers across the globe to benchmark performance and assess the effectiveness of processes.

Quality needs to be part of that mix. Because measurements like efficiency and productivity don’t necessarily mean high quality, incorporating ways to ensure quality from the start can help to eliminate waste and rework.

Manufacturing quality is achieved through quality control using documented, repeatable, and measurable processes.

What if you could incorporate quality control in every operation, at every work center to not only ensure high-quality finished goods but also simultaneously train high-quality operators?

Introducing Crossroads’ ERP independent solution, VJES (Visual Job Execution Software). VJES is an electronic work instruction interface between engineering and the paperless manufacturing floor. VJES makes available only one version of the work instructions – the RIGHT one. By deploying up-to-date, visually rich work instructions, images, and videos, VJES gives production personnel the best opportunity to build it right the first time and provides a way to track worker productivity during the build at every step.

VJES Overview

VJES achieves RESULTS:

  • Turn new hire welders into specialized welders in 2 weeks
  • Improvement of quality score from 68/100 to 93/100 in 12 months
  • During the first month of use, employee training timeframe improved from 1 week, to 3 days.
  • First pass yield percentage at 100% for 8 months straight this year.
  • Able to incorporate a quality cell after productivity increased due to newfound bandwidth received when adopting VJES.


Request a demo or Contact us to learn more.

Print
8900 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories