The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

BPCS/LX Tip of the Week: The Machine Master Part 2

Anthony Etzel 0 49391 Article rating: No rating
Understanding:

The Machine Master File

Do your machines have a fixed asset tag? The machine master file has a field called Fixed Asset.

BPCS does not use this field, so you can use this field for anything. You can record your fixed asset tag in this field and use the effective date. You can create a custom fixed asset list by using a DFU or Query program.

Baan/LN Tip of the Week: Business Partner Structures

Kathy Barthelt 0 63243 Article rating: No rating

In ERP LN, users can define a distributed business partner organization by defining parent business partners to link the business partners with different roles.

In Baan IV, users can define a distributed business partner organization in the Maintain Concern Structure of Trade Relations (tccom3101m000) session.

Harsco Rail Goes Live With the RMC3 Data Collection Solution

Crossroads RMC 0 31872 Article rating: No rating

Harsco Rail, an industry leader in the railway track maintenance, has completed the first phase of their implementation of the Crossroads RMC Data Collection Solution for Baan V. The initial implementation included receiving and putaway. Harsco’s data collection project manager reports, “When I ask them (the users) how it’s going, they smile. I have had nothing but very positive feedback. It’s been very uplifting for me to work on this project and have it so well received.” The next phase of the implementation will include Report Operations Complete, Inventory Transfers, and Stock Inquiry.

Baan/LN Tip of the Week: Tax Exemption Certificates

Kathy Barthelt 0 61924 Article rating: No rating

In Baan IV, tax exemption processing is supported only on sales orders for non-tax provider users.

In Infor LN, tax exemption certificate processing is also performed for purchase orders, and for sales orders if users use a tax provider.

Users can define tax-exemption certificates in the following sessions:

  • Tax Exemptions for Sales (tcmcs1142m000)
  • Tax Exemptions for Purchasing (tcmcs1560m000)
  • Register Warehouse for Tax Exemptions (tcmcs1561m000)

 

BPCS/LX Tip of the Week: The Machine Master Part 1

Anthony Etzel 0 48997 Article rating: No rating
Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.

Baan/LN Tip of the Week: Aborted Finalization Run

Kathy Barthelt 0 63109 Article rating: No rating
When a finalization run is aborted and in the batches selected for this finalization run are transaction types having the update mode finalization, you must use the Restart Finalization Run session. This session can be found in the Transaction Processing menu of the General Ledger Module of the Finance Package.

BPCS/LX Tip of the Week: SFC600

Anthony Etzel 0 49984 Article rating: No rating
In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.
RSS
First163164165166168170171172

Theme picker

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Print
15096 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories