Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

George Moroses 0 24214 Article rating: 5.0

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand.....

Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

Kathy Barthelt 0 14641 Article rating: 5.0

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Infor LX & BPCS Tip: Changing an item to non-inventory

George Moroses 0 11448 Article rating: 5.0

When an attempt is made to change an item’s type to a non-inventory item from any other value, a new validation is performed to determine if the item has any inventory on hand and, if so, prevents changing the item’s type.

This enhancement available in LX 8.4 prevents LX from showing an on-hand inventory balance for a non-inventory item.

The programs or areas impacted include:

  • Facility/Planning Data Maintenance, MRP140D2
  • IDF Enterprise Item

To get this enhancement, request and apply MR 80120.

Top 10 Things (you might not know) About Crossroads RMC

Crossroads RMC 0 12002 Article rating: 5.0


10.  Crossroads RMC has been in business since 1984 & has been an  partner since 1991
 

 9. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽

 8.  Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓

 7.

 6.

 5.

 4.

 3.

 2.

 1.

DATA: See it. Understand it. Discuss it.

Crossroads RMC 0 12898 Article rating: 5.0

We’ve all heard author and management consultant Peter Drucker’s famous quote “If you can’t measure it, you can’t manage it.”  

What’s the right way to manage “It” though? Is it enough to put the data in the hands of the responsible manager and wait for change to occur? Does the manager have a pulse on everything that went into those numbers?

Your numbers tell a story, but there is a lot of...

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 13777 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

RSS
First1213141517192021Last

Theme picker

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip: Support for IBM i 7.3 and Infor LX Products

On September 30, 2022, IBM® announced the end of support of IBM i operating system 7.3 effective September 30, 2023. In line with IBM’s support policy, Infor will no longer support LX and related products on IBM i 7.3 after May 31, 2024. All Infor LX releases, patches, and related solutions are planned to be delivered and compiled at IBM i 7.4, effective June 1, 2024. These deliverables will install and function on version 7 release 4 (IBM i 7.4) and above. This will require that your operating system is at a minimum release level of IBM i 7.4.

This policy extends to other Infor LX-related technologies including WebTop, System i Workspace (SiW), and Infor Development Framework (IDF).

Action Steps If you have not done so already, we recommend that you start planning and completing your upgrade to IBM i 7.4 or above prior to June 1, 2024. After this date, if you register a support call with Infor Support, and your application still runs on IBM i 7.3 or older, you may be requested to upgrade to a supported version of the IBM i operating system.

In addition, we invite you to log on to Infor Support to view and download important information regarding Infor LX. Knowledge Base (KB) articles have been created to proactively provide you with information regarding this Announcement. ​Please consider clicking on the “Subscribe” feature within each KB article to receive notifications. Once you have subscribed, you will receive notifications when they are updated.

  • View KB article 1397381 | Infor LX Product Bulletins and Announcements
  • View KB article 1947086 | Infor BPCS/LX Product Lifecycle Policy


If you need assistance in planning this project, Crossroads RMC is happy to help you strategize, and create project plans, test plans, 3rd party product due diligence, and cutover assistance. Contact us today to learn more. 800.762.2077  | solutions@crossroadsrmc.com