Baan/LN Tip of the Week: The Product Configurator

Kathy Barthelt 0 49182 Article rating: No rating

What is it?
The configurator consists of a set of features (questions). The options (answers) to these questions are used to generate the custom bill of material and routing. These questions may be answered at the time of order entry, prior to order entry (in a project or quote) or after order entry (in the project). The order of the questions do not need to have any relationship to the bill of materials. The configurator may also calculate the selling price, create a unique “smart” item number, custom description and text. Simple rules are used to interpret the answers.

Who uses the configurator?
Companies whose products have options. The configurator eliminates the need for part numbers for all combinations of options. The configurator ensures that the pricing and bills are correct. The configurator also keeps statistics on the frequency the options are selected.

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Anthony Etzel 0 17146 Article rating: No rating

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have set up your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished, and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are set up and what transactions along with their frequency are captured.

PDIC selects NextTrack Dashboard for Costa Rica Wire Plant

Anthony Etzel 0 45491 Article rating: No rating

The Analytics Dashboard will be used in combination with the existing Crossroads MES system to provide real time machine status across the plant. In addition, KPI’s like OEE and Downtime % will be monitored and displayed at the wire machines and to the production management.

BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 52971 Article rating: 4.5

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 59841 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 66426 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 49236 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 41180 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

RSS
First163164165166167168169171

Theme picker

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

Beyond the Four Walls—Achieving Upstream and Downstream Inventory Visibility

Infor LX | BPCS | Infor LN | Baan | Infor M3

When an enterprise has many suppliers, dealers/distributors, and customers spread out across the globe, it becomes important that it gains better visibility into inventory outside of its direct ownership and control, on both the supply and demand side. On the supply side, the company has outstanding POs and needs reliable estimates of when those will ship, as well as early indications whenever there will be delays in shipment. Once shipped, updates on the estimated time of arrival (ETA) are important, particularly when there are delays.

This external visibility is even more important during times of disruption. Early visibility into disruptions in supply or rapid changes in demand is key to providing the intelligence to drive agility. By responding earlier, faster, and with more accurate intelligence, a company has more options, makes smarter decisions, and avoids catastrophes.

How do you get that visibility? Here are some options…

• EDI—EDI can provide POs (EDI 850) for orders, ASNs (EDI 856) to communicate what has been shipped, Inventory Inquiry/Advice (EDI 846) with updates to on-hand inventory at various holding locations, including status (on hand, committed, on order, etc.), forecasts (e.g. EDI 830 planning schedule with release), shipping schedules, and other useful information about inventory in transit or at rest. EDI can be challenging for a smaller company to implement, especially without the right partner and solution. For this reason, not all suppliers or customers will necessarily have EDI. In those cases, an alternate approach, such as a portal, is needed to serve the remaining non-EDI trading partners.

• Supplier and Customer Portals—Portals provide a way for suppliers or customers who do not have EDI capabilities to update inventory, production, and order status. This requires some training and communications so that the trading partners use the system consistently, properly, and in a timely manner. (Portals to ERP for Infor LN & Baan Only)

• External Inventory Locations/Accounts—Some ERP systems allow supplier or customer stocking locations to be set up within the solution, so those locations look like another distribution center or plant, but with the inventory in those locations not being owned by the company. Personnel at the supplier or customer can then be given an account within the ERP system to update their inventory information. The account may provide additional functionality to the supplier or customer as well. If the trading partner actively uses the system to run a part of their operations, the data are more likely to be timely and accurate.

• API Integration—Trading partners may provide inventory data via an API in the ERP system.

• Planning Solutions—provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time. (OTTO - On Time Orders for Infor LX, BPCS & M3 Only)

Now more than ever, good inventory management, with accurate inventory data, is a core element of success for manufacturers and wholesale distributors. Having the right products, in the right place, at the right time, in the right quantities—and doing so at a low cost—drives profitability, cash flow, customer loyalty, and success for a company. This can be a difficult balancing act, especially when demand is volatile and supply disruptions occur. It can be achieved with the right inventory strategy, process disciplines, risk management, and capable systems in place. Excellence in inventory management, with the right systems, is key to enabling businesses to survive in challenging times and thrive in the market during good times.

Not sure where to start? Crossroads RMC consultants have expertise with all of the options listed above and can help you realize optimal inventory management, regardless of the size of your organization. 800.762.2077, solutions@crossroadsrmc.com, or ask us to contact you.

Print
23270 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

x

Categories