Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

George Moroses 0 24702 Article rating: 5.0

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand.....

Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

Kathy Barthelt 0 15153 Article rating: 5.0

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Infor LX & BPCS Tip: Changing an item to non-inventory

George Moroses 0 11929 Article rating: 5.0

When an attempt is made to change an item’s type to a non-inventory item from any other value, a new validation is performed to determine if the item has any inventory on hand and, if so, prevents changing the item’s type.

This enhancement available in LX 8.4 prevents LX from showing an on-hand inventory balance for a non-inventory item.

The programs or areas impacted include:

  • Facility/Planning Data Maintenance, MRP140D2
  • IDF Enterprise Item

To get this enhancement, request and apply MR 80120.

Top 10 Things (you might not know) About Crossroads RMC

Crossroads RMC 0 12392 Article rating: 5.0


10.  Crossroads RMC has been in business since 1984 & has been an  partner since 1991
 

 9. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽

 8.  Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓

 7.

 6.

 5.

 4.

 3.

 2.

 1.

DATA: See it. Understand it. Discuss it.

Crossroads RMC 0 13123 Article rating: 5.0

We’ve all heard author and management consultant Peter Drucker’s famous quote “If you can’t measure it, you can’t manage it.”  

What’s the right way to manage “It” though? Is it enough to put the data in the hands of the responsible manager and wait for change to occur? Does the manager have a pulse on everything that went into those numbers?

Your numbers tell a story, but there is a lot of...

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 14230 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

RSS
First1314151618202122Last

Theme picker

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Ways to Prevent Scrap & Rework From Costing You

Scrap and rework costs are a manufacturing reality impacting organizations across all industries and product lines.

Scrap and rework costs are caused by many things—when the wrong parts are ordered, when engineering changes aren’t effectively communicated or when designs aren’t properly executed on the manufacturing line.

No matter why scrap and rework occurs, its impact on an organization is always the same—wasted time and money. And while no one, especially an operations manager, wants to admit it, these expenses add up quickly and negatively impact the bottom line...

Read Full Article
Previous Article Tip of the Week: 8 Common-Sense Rules for Inventory Management
Next Article Baan/LN Tip of the Week: What is your M.O.?
Print
40248 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories