IDF News: IDF Maintenance

George Moroses 0 32822 Article rating: 5.0

The Infor Development Framework (IDF) provides two options that you can use to review information about jobs that are in the job queue or underway at the workstations and change the status of unattached jobs or review detailed information for specific unattached jobs.

                Option 5 – Job Status Maintenance: Use this option to review information about jobs that are in the job queue or underway at the workstations. You can also delete records of jobs in the Job Activity (JOBACT) file.

                Option 6 – Unattached Job Status Maintenance: Use this option to change the status of an unattached job. You can also review detail information for a selected unattached job.

About 65% of the world’s population are visual learners. This extends into the ERP software realm, too.

Infor LX & BPCS

George Moroses 0 38161 Article rating: 5.0

Graphical representation makes complex concepts—like the intricacies of an ERP system—more universal, relatable and easy to understand.

ERP dashboards gather and visualize critical metrics from across the organization, offering insight into the performance, outlook and interconnectivity of business processes.

By setting up ERP dashboards that illustrate key metrics and compellingly communicate operational performance, key stakeholders will have a clear picture of the health of the business—and make better, more informed business decisions as a result.

The Crossroads Analytics Dashboard has preconfigured views for all of the following:

 Infor LX & BPCS
  • Sales Bookings (ECH)
  • Accounts Receivable (RAR)
  • Accounts Payable (APH)
  • Planned Orders (KFP)
  • Purchasing (HPH)
  • Shop Order Material (FMA)
  • Shop Order Operations (FOD)
  • CEA
  • Order Booking (ECS)
  • Labor History (FLT)
  • Sales History (SIH)
  • Material Status (IIM/ILI)

To learn more visit our Analytic Dashboard webpage.

Consulting News: How do I identify the processes that impact my ERP upgrade?

Crossroads RMC 0 40465 Article rating: 5.0

Identify all of the processes that impact my ERP upgrade

  • Identify all current users that transact/execute transactions
    • List users by transaction type/functional area
    • List users by shift worked (off-shift resources often support multiple areas/functions)
    • List users by time frame of use (Daily, Weekly, Monthly, Annually)
       
  • Identify all users that receive reports from the system
    • List last run date of all reports, queries and owners
       
  • Identify all data extract programs/routines
    • Downloads to Excel/Access databases
    • Downloads to Labor / Payroll Reporting Systems
    • Downloads to Assets Management Systems
    • Downloads to Third Party Logistics partners
    • EDI messages for requirements downloads to vendors
    • EDI Input for Order Entry, ASN, and Quotes.
    • Downloads/uploads to vendor Quality Management Systems

Infor LX & BPCS Tip of the Week: MPS vs. MRP

George Moroses 0 40203 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor/ERP LX will calculate cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

You’ve got a handle on your inventory requirements, right? Are you confident you can handle a rush order, or ten rush orders?

Baan & LN Add-Ons

Kathy Barthelt 0 30444 Article rating: 5.0

RMCbuild gives you the ability to report a component’s gross requirement, shortage, on-hand inventory, on-order inventory, allocated inventory, inspected inventory, production or work orders due to replenish component inventory, buyer or planner, and/or item group… and more.

RMCbuild takes all the surprise and guess work out of inventory planning. Give your employees the tools they need to do their job effectively.

Avalara isn't only tax calculation and returns filing....

Baan & Infor LN

Kathy Barthelt 0 35375 Article rating: 5.0

Did you know that in addition to tax calculation and returns filing, Avalara can also help with:

  • Business license and tax registration
  • Streamlined Sales Tax qualification
  • Nexus analysis and compliance
  • Tax document management including exemption certificates
  • Audit preparation

Contact us today! We partner closely with Avalara to provide you with solutions on ALL version of Baan and Infor LN!
 

Infor LN & Baan: Is Your House All In Order?

Kathy Barthelt 0 27864 Article rating: 5.0

Have you successfully closed all of the fiscal, tax and reporting periods for 2019 and closed the year? Sometimes this task hangs out there looming because either people don’t know what needs to be done, or there is a fear there are going to be problems.

Let Crossroads RMC’s expert finance consulting team help you through this.

Move into 2020 with ease! Contact Kathy Barthelt today to put together a plan for your close.
800.762.2077

RSS
First4243444547495051Last

Theme picker

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Aborted Finalization Run

When a finalization run is aborted and in the batches selected for this finalization run are transaction types having the update mode finalization, you must use the Restart Finalization Run session. This session can be found in the Transaction Processing menu of the General Ledger Module of the Finance Package.
Previous Article Baan/LN Tip of the Week: Restricted User Access
Next Article Baan/LN Tip of the Week: Tax Exemption Certificates