Previously, a user was able to complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600.

This enhancement verifies the user security settings that were set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and complete the cost transfer process. This enhancement provides security in CST920 that prevents incorrect cost transfers from being processed.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: Inventory Transaction Post to G/L by Cost Type

Anthony Etzel 0 23745 Article rating: No rating

This enhancement provides a method to post material, labor and overhead values on inventory postings to the general ledger to meet financial reporting requirements. The solution provides an optional further breakdown of cost by cost bucket using the new G/L Cost Type.

The benefit this program provides is the ability to post detailed material, labor, and overhead values during inventory posting to the general ledger to meet financial reporting requirements. It also helps isolate import and transport cost elements required by some countries. Global companies with intercompany purchasing are able to isolate material costs so that it is eliminated at a consolidated level.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Inventory Tracking

Kathy Barthelt 0 39428 Article rating: No rating

Do you have a good handle on your inventory? Do you know when products need to be reordered and which are on their way? Are you able to find inventory easily within your facility, or are items getting misplaced and then unnecessarily reordered? Having a good inventory system in place will avoid unnecessary costs and save lots of time. We’ve been helping customers with this for over 20 years. Let us know if you need help getting started.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: How is Your Productivity?

Kathy Barthelt 0 38050 Article rating: No rating

Are your employees not as productive as you’d like them to be? 
Are jobs not getting completed on schedule? 

Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

RSS
First7879808183858687Last

Theme picker

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Performance Standard Cost

by Infor

Everything you ever wanted to know about Calculating Standard Cost and Actualizing Standard Cost / Revaluing Inventory (ticpr2210m000 | ticpr2220m000)

Calculating standard cost and re-valuing inventory are important capabilities within your Infor ERP system for a variety of reasons. Sometimes these sessions experience performance issues. Here is a brand new PowerPoint released by Infor to discuss both the functional and technical side of these sessions. Get every last what, where, why, and how answered so that you can improve how these sessions run on your system.

Download Infor PowerPoint>

Previous Article Infor LN & Baan Tip: Latest Porting Set – All Versions of Infor LN & Baan
Next Article Infor LN & Baan Tip: Did you know? PBOM – Effective Dates
Print
27169 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories