Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt

Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LX / BPCS Tips & Tricks for EXECUTIVES
Print
14953 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

1345678910Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

1345678910Last

Theme picker

Categories